QUESTION NO: 1
Which of the following would be included in a project scope document? (Select THREE).
A. Project constraints
B. Gantt chart
C. Work Breakdown Structure (WBS)
D. Project roles and responsibilities
E. Key Performance Indicators (KPIs)
F. Detailed project objectives

Answer: D, E, F
QUESTION NO: 2
An ongoing project has a BAC of $450,000, an EV of $110,000 and an AC of $100,000. Which of the following is the CPI of the project?
A. $340,000
B. 1.1
C. $10,000
D. .91
Answer: B

QUESTION NO: 3
The project manager has been informed that the project team cannot procure any more materials until a new purchase order has been received. The project manager should record this information in which of the following documents?
A. Risk response plan
B. Communications plan
C. Issues log
D. Change control log
Answer: B

QUESTION NO: 4
Which of the following documents should be used to present the length of identified tasks?
A. CPM
B. Key event/activity list
C. PERT
D. Gantt
Answer: A

QUESTION NO: 5
Before a change request is presented to the change control board, which of the following should the project manager do? A+ Exams

A. Suggest the hoard study the cost of the change.
B. Evaluate the affect on all other parts of the project.
C. Review the change request with the project sponsor.
D. Request team member input on the value of the change.
Answer: C